Category Archives: Updates

July 19 | Rio Grande Campus Renovations

In June, construction crews completed demolition on the center area structure and formwork for the ACCelerator slab. At the bottom level, steel columns were erected, plumbing and electrical risers were installed, and wall framing and … Continue reading

July 2019 | ACC Highland Phase 2

Construction crews continue to work over the summer on the Highland Campus Phase 2 renovation project, including waterproofing exterior openings, pouring sound slabs and ramps, open stair steel installation, and reinstalling permanent fencing around the … Continue reading

June 2019 | Rio Grande Campus Renovations

Construction crews continue to make progress on the Rio Grande Campus renovations. In May, shoring — the process of temporarily supporting a building with props during alterations — was completed at the south mechanical room … Continue reading

May 2019 | ACC Highland Phase 2

ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent … Continue reading

April 2019 | Rio Grande Campus Renovations

Construction work continues to move forward on Rio Grande Campus. Waterproofing has been completed in the north atrium and has commenced in the south atrium. Underground electrical and plumbing also has started in both atriums. … Continue reading

April 2019 | ACC Highland Phase 2

Construction crews continue work on Highland Campus Phase 2. The structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo … Continue reading

March 2019 | Rio Grande Campus Renovations

At Rio Grande Campus, crews have completed pouring walls at the north basement mechanical room and are working on electrical and telecom systems. Metal wall framing also has gone up on the second and third … Continue reading

March 2019 | ACC Highland Phase 2

At ACC Highland Phase 2, construction teams continue work on framing, steel erection, and the exterior shell. Exterior window installation also continues, along with mechanical, electrical, and plumbing work.

February 2019 | Rio Grande Campus Renovations

Construction crews continue work on the lower level, including mechanical/electrical/plumbing overhead and chilled beam installation. The mechanical room slab in the north atrium and the underground electrical duct bank have been poured. Interior wall framing … Continue reading

February 2019 | ACC Highland Phase 2

Construction continues on phase 2 at ACC Highland. Crews completed the removal of floor finishes in January and are now re-pouring concrete that was in disrepair. Work also continues on the new television studio and … Continue reading

Back to Top