December 2018 | ACC Highland Phase 2

Phase 2, which will add 415,000 square feet of flexible advanced facilities, features a creative digital media center, a health sciences/STEM regional simulation center, continuing education and workforce centers, and a culinary arts and hospitality management center with a student-operated restaurant. Crews are about 50 percent complete on a number of lower-level projects including mechanical/electrical/plumbing overhead and interior wall framing. Steel construction also is approximately 50 percent complete. Roofing installation is now underway. The metal roof deck is approximately 50 percent installed and air handling units in the three rooftop penthouses will be installed by end of January.