January 2019 | ACC Highland Phase 2

Demolition of the southeast portion of the building is complete, and construction on the college’s drama and dance departments and assembly areas for occupancy load, vibration, and clear-span of columns/beams is underway. Steel erection, roofing, and underground utility work are ongoing.

Concrete has been poured for the meeting presentation hall and music performance hall and elevator shafts are complete. Mechanical, electrical, and plumbing work is 55 percent installed.

Tags: , ,

Back to Top