July 19 | Rio Grande Campus Renovations

In June, construction crews completed demolition on the center area structure and formwork for the ACCelerator slab. At the bottom level, steel columns were erected, plumbing and electrical risers were installed, and wall framing and mechanical/electrical/plumbing installation were started. On the first level, stairs were poured at the northeast entrance and underground plumbing on the southeast side was completed. Crews also installed beams and finished steel infill for the roof openings. Activities for July include beginning work on the elevator shaft and filling in the roof openings.