May 2019 | ACC Highland Phase 2

ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent complete. In the paseo, exterior framing and sheathing is ongoing. The paseo stairs and roof connector bridge also have been poured. Waterproofing at all exterior openings is complete, minus the paseo area. Concrete walls at the performance hall are currently being installed. Interior framing; sheetrock installation; and mechanical, electrical, and plumbing work are all ongoing. Underground utility trenching is scheduled to begin soon.