May 2019 | Rio Grande Campus Renovations

Renovations are moving forward at Rio Grande Campus. The contractor is installing formwork in preparation for pouring an elevated concrete slab which will become a new floor level for the future Student Commons space. Walls have been poured at the north atrium and the south mechanical room. Additionally, air conditioning equipment has been delivered and set in the basement. Grading and electrical rough-in also has started in the ACCelerator. Steel framing is ongoing on levels one and two.