September 2019 | ACC Highland Phase 2

The chilled water pipes have been flushed and a portion of the building now has conditioned air. Interior finishes are progressing. The ceiling grid and light fixtures are beginning to be installed. The glass handrails at the floor openings are being installed. Wall and floor tile have begun. Door frames and hollow metal window frames, as well as glass, continue to be installed. The concrete floors in certain areas have been ground smooth and will be polished. The kitchen hoods are installed in the Culinary area. Meanwhile, the interior southern portion of the building is framed and infrastructure is nearly complete.