» constructionACC 2014 Bond Projects

March/April 2020 | Rio Grande Campus Renovations

The COVID-19-related shutdowns have really created a challenge for our team to keep construction progress moving forward, but we’ve been fortunate that no major issues have arisen thus far, except for feeling the impacts of … Continue reading

March/April 2020 | ACC Highland Phase 2

The Riverbat has been installed on the Paseo canopy. It casts a shadow below that moves across the Paseo throughout the day. Concrete placement on the west side is finishing up. Grading and concrete work … Continue reading

February 2020 | ACC Highland Phase 2

Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. … Continue reading

February 2020 | Rio Grande Campus Renovations

Persistent rainy, damp conditions slowed the rate of progress a bit in February, but construction continued to progress well. Spray foam insulation applied to exterior walls has been completed on levels 1 and 2 and … Continue reading

March 2019 | Rio Grande Campus Renovations

At Rio Grande Campus, crews have completed pouring walls at the north basement mechanical room and are working on electrical and telecom systems. Metal wall framing also has gone up on the second and third … Continue reading

Crews begin construction

Construction crews have started the next phase of development at Elgin Campus. Site work for the project currently includes moving dirt, trenching, leveling off land, etc. Phase 2 is scheduled to be completed for classes … Continue reading

Back to Top