November 2020 | ACC Highland Phase 2

Construction is substantially complete while final testing and commissioning of all systems are still ongoing. Final corrections/touchups and final cleaning are occurring as well. Departmental moves have begun and faculty and staff are starting to set up their spaces prior to the start of the spring semester beginning in January 2021. The building remains closed to the general public as there is still a lot of activity inside getting things finished and set up.

October 2020 | ACC Highland Phase 2

Construction is nearly substantially complete. Final testing and commissioning of all systems are still ongoing. Final corrections/touchups and final cleaning are occurring as well. The telescopic seating for the Dance Studio will be installed soon. Equipment is still being installed throughout the building and furniture is being placed in its correct location throughout also. Computer installation will be forthcoming. Departmental moves will begin soon so that faculty and staff may set up their spaces prior to the start of the spring semester beginning in January 2021.

September 2020 | ACC Highland Phase 2

The Black Box Theatre wood floor is being installed. The wood stage flooring in the Music Performance Hall will be installed soon. The fixed seating in the performance spaces is being installed. Final touches and last-minute finishes are being completed. The mechanical and electrical systems have had a final inspection. The plumbing and fire alarm systems are being tested and will be inspected soon. The majority of the furniture has been installed and equipment installation is well underway. The exterior furniture has been installed as well.

July/August 2020 | ACC Highland Phase 2

Construction is nearing completion with a substantial completion milestone expected at the end of September. Final touches are being completed throughout the building with several large performance spaces still undergoing substantial construction activities. Curtain tracks are being hung. The wood sprung dance floor will be installed soon. Fixed seating is starting to be installed in some locations. The pipe grid is nearly complete in all areas.

The connections to adjacent buildings 1000 and 4000 have been completed. Landscaping and site paving is mostly complete. Exterior furniture has been installed. The majority of the furniture has been delivered and installed. Equipment installation has begun in some areas.

May/June 2020 | ACC Highland Phase 2

The exterior walkways, seating walls, and landscaping are complete on the west and are underway on the east side. The exterior building finishes are being completed and exterior furnishings are forthcoming.

The majority of the interior spaces are complete or nearly complete with the exception being the larger performance and production spaces that have a multitude of infrastructure and acoustic components and specialty finishes. Touch-ups and final cleaning efforts are on-going. Furniture installation is nearing completion throughout the building. Equipment installation has begun in the health sciences simulation area. Commissioning and systems testing is on-going.

Highland Phase 2 will open for Spring Semester 2021.

February 2020 | ACC Highland Phase 2

Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. Restroom accessory installation is about to begin. Tile work, carpet, and other flooring activities are ongoing. Decorative metal railing posts have been installed at the open stairs and perforated panels will be installed in March. Glass railing at floor openings is complete. Three of the five elevators are complete. Cable tray installation, wire pulling, and pipe insulation are nearly complete.

Exterior metal panel activities are ongoing on the upper paseo. Paseo waterproofing is nearly complete and elevated concrete topping slab will be poured soon afterward. Sitework is currently ongoing in the paseo and on the west side. Sidewalks are being installed. Landscaping and finishes to begin shortly.

January 2020 | ACC Highland Phase 2

Paseo from the west

Interior
Gas service is now on in the building and plumbing fixtures are being installed. Overhead utilities are still underway in the southern portion of the building. Restroom tilework is making progress, as well as carpet tile in many office suites and study rooms. Ceiling tile installation has begun and acoustic panels are currently in progress in the main corridors. Stair railings continue to be installed. Millwork, such as cabinetry and built-in reception desks, is being installed.

Exterior
The building exterior metal wall panel installation is still in progress. Exterior site grading and flatwork have begun.

December 2019 | ACC Highland Phase 2

Drywall work is nearing completion and elevator installation is wrapping up soon. Railings at floor openings and stairs are well underway. Crews are now installing restroom fixtures and toilet partitions. Installation is complete for the majority of interior door and window frames as well for as the walk-in coolers and freezers for the culinary kitchens. Many of the faculty office suites are receiving finishes such as paint, carpet, millwork, and ceiling grid. In the southern portion of the building, overhead utilities are underway. The building exterior metal wall panel has begun in the Paseo.

November 2019 | ACC Highland Phase 2

Overhead doors are being installed and the majority of the exterior curtain wall and stucco work are completed. Exterior grading and flatwork have begun. The exterior and interior stair railings are currently being installed. The culinary kitchen equipment will be set on the roof soon. Acoustic panels are in progress in the main corridors. Elevator installation is ongoing and the insulation for the metal wall panels at the paseo are being installed. The waterproofing at the upper-level paseo concrete is underway.

October 2019 | ACC Highland Phase 2

The interior wall framing is almost complete and sheetrock work is expected to wrap by mid-November. Many interior walls have been primed and painted. Interior and exterior doors are being hung. Ceiling grid installation is continuing and mechanical components, including chilled beams, light fixtures, etc., are being dropped into the ceiling grids. The majority of the elevators also have been installed. The Paseo on Phase 2 is taking shape with grading underway. Exterior concrete paving will begin shortly. The project remains on schedule to open for fall 2020 next August.