January 2020 | ACC Highland Phase 2

Paseo from the west

Interior
Gas service is now on in the building and plumbing fixtures are being installed. Overhead utilities are still underway in the southern portion of the building. Restroom tilework is making progress, as well as carpet tile in many office suites and study rooms. Ceiling tile installation has begun and acoustic panels are currently in progress in the main corridors. Stair railings continue to be installed. Millwork, such as cabinetry and built-in reception desks, is being installed.

Exterior
The building exterior metal wall panel installation is still in progress. Exterior site grading and flatwork have begun.

San Gabriel Campus | Campus Installation Continues

Crews are finalizing installation throughout campus in April. The irrigation and landscape subcontractor also continues work at bio-retention ponds. The planting of trees continues and crews completed the installation of all three water collection tanks on site. A grand opening celebration is scheduled for the end of May.