Update – Rio Grande Campus Parking Garage

The progress continues for the RGC Parking Garage.  The 2nd concrete pour will occur early morning on January 28 and the 3rd concrete pour is scheduled for January 30.  Each concrete pour accounts for half of one floor.  There will be a total of 14 concrete pours.

SpawGlass Contractors remains on time, on budget, and without any injuries on the jobsite.