Update – Rio Grande Campus Parking Garage

The concrete for the west half of the 5th floor will be poured this week leaving 5 additional concrete pours remaining. SpawGlass remains on schedule to complete construction in August 2009 for the Fall semester. Permitting for the utility work to upgrade the water line along 12th Street to Rio Grande Street and to add the 7th level to the Garage is still in progress. Masonry work is scheduled to begin soon.