Update – Rio Grande Campus Parking Garage

Update (4-27-09):

SpawGlass made 2 concrete pours last week to make up for rain the previous week.  The final concrete pour will be this week (weather permitting) to complete the 7 level parking structure.  Any additional concrete pours will be made during the day for pouring the stairs, canopies, and misc. leave-outs.  The project remains on schedule to open in August 2009.

RGC Construction site taken at ground level across 12th Street

RGC Construction site taken at ground level across 12th Street

RGC Garage Construction - Aerial Photo

RGC Garage Construction - Aerial Photo

RGC Garage Construction - Aerial Photo

RGC Garage Construction - Aerial Photo

RGC Garage Construction - Aerial Photo

RGC Garage Construction - Aerial Photo

Back to Top