Update – Rio Grande Campus Parking Garage 9

6/10/09 Update:

The crane was dismantled the weekend of May 30-31.  Miscellaneous concrete is being completed.  Storefront and glazing work is ongoing as well as sprinkler work and miscellaneous steel work.  The elevator installation began this week.  The water line upgrade along 12th Street is underway.  SpawGlass remains incident/accident-free and the project is still on schedule for completion in August 2009.

acc-rio-grande-parking-garage-06-2009-1 acc-rio-grande-parking-garage-06-2009-2 acc-rio-grande-parking-garage-06-2009-3

Back to Top

4 Responses to "Update – Rio Grande Campus Parking Garage 9"