Daily Archives: April 5, 2012

April 2012 Update – Hays Campus

The design development phase was completed in late March. The architectural firm Gensler issued a package of full-size design development review packages at the 50 percent and 100 percent complete level for ACC departmental review … Continue reading

ACC Approves $45 Million in Bonds for Campus in Kyle

Austin American-Statesman – ACC Approves $45 Million in Bonds for Campus in Kyle

ACC Issues Bonds for Hays Campus

San Marcos Mercury – ACC Issues Bonds for Hays Campus

ACC Approves $45 Million in Bonds for Hays Campus

Austin Business Journal – ACC Approves $45 Million in Bonds for Hays Campus

March 2012 – Elgin Campus Update

The crawl space mudslab and first-floor slab have been poured. Steel erection will begin by the middle of April. Underground utilities are still in progress. The driveways and parking lots will be poured in the … Continue reading