July/August 2020 | ACC Highland Phase 2

Construction is nearing completion with a substantial completion milestone expected at the end of September. Final touches are being completed throughout the building with several large performance spaces still undergoing substantial construction activities. Curtain tracks … Continue reading

July/August 2020 | Rio Grande Campus Renovations

Tremendous progress has been made over the past month. The two elevators are being installed. Decorative hand railing systems are being installed in the interior stairwells. The terrazzo floors in all common areas on Levels … Continue reading

May/June 2020 | Rio Grande Campus Renovations

Overall, construction is about 85 percent complete. Interior Laboratory casework installation is nearly complete in the science labs on Levels 1-3. All interior walls on Levels 0 and 1 have been constructed, which includes being … Continue reading

May/June 2020 | ACC Highland Phase 2

The exterior walkways, seating walls, and landscaping are complete on the west and are underway on the east side. The exterior building finishes are being completed and exterior furnishings are forthcoming. The majority of the … Continue reading

March/April 2020 | Rio Grande Campus Renovations

The COVID-19-related shutdowns have really created a challenge for our team to keep construction progress moving forward, but we’ve been fortunate that no major issues have arisen thus far, except for feeling the impacts of … Continue reading

March/April 2020 | ACC Highland Phase 2

The Riverbat has been installed on the Paseo canopy. It casts a shadow below that moves across the Paseo throughout the day. Concrete placement on the west side is finishing up. Grading and concrete work … Continue reading

February 2020 | ACC Highland Phase 2

Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. … Continue reading

February 2020 | Rio Grande Campus Renovations

Persistent rainy, damp conditions slowed the rate of progress a bit in February, but construction continued to progress well. Spray foam insulation applied to exterior walls has been completed on levels 1 and 2 and … Continue reading

Steel Roof Supports South Atrium

January 2020 | Rio Grande Campus Renovations

Construction teams commemorated the topping-out of Rio Grande Campus on Wednesday, January 22. The event marked an important milestone for the project. Exterior On Level 2, exterior wall spray foam was placed on all facades. … Continue reading

Paseo from the west

January 2020 | ACC Highland Phase 2

Interior Gas service is now on in the building and plumbing fixtures are being installed. Overhead utilities are still underway in the southern portion of the building. Restroom tilework is making progress, as well as … Continue reading