Overall, construction is about 85 percent complete. Interior Laboratory casework installation is nearly complete in the science labs on Levels 1-3. All interior walls on Levels 0 and 1 have been constructed, which includes being … Continue reading
May/June 2020 | ACC Highland Phase 2
The exterior walkways, seating walls, and landscaping are complete on the west and are underway on the east side. The exterior building finishes are being completed and exterior furnishings are forthcoming. The majority of the … Continue reading
March/April 2020 | Rio Grande Campus Renovations
The COVID-19-related shutdowns have really created a challenge for our team to keep construction progress moving forward, but we’ve been fortunate that no major issues have arisen thus far, except for feeling the impacts of … Continue reading
March/April 2020 | ACC Highland Phase 2
The Riverbat has been installed on the Paseo canopy. It casts a shadow below that moves across the Paseo throughout the day. Concrete placement on the west side is finishing up. Grading and concrete work … Continue reading
February 2020 | ACC Highland Phase 2
Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. … Continue reading
February 2020 | Rio Grande Campus Renovations
Persistent rainy, damp conditions slowed the rate of progress a bit in February, but construction continued to progress well. Spray foam insulation applied to exterior walls has been completed on levels 1 and 2 and … Continue reading
Districtwide electrical system updates continue
Work on air-conditioning and ventilation systems at Cypress Creek Campus is underway; a second phase of the work will be performed before the fall semester. Electrical system upgrades and preventative maintenance are ongoing at Pinnacle … Continue reading
Elgin site work progresses
Building foundations have been poured, underground utilities are being installed, and miscellaneous site work, such as perimeter drain installation, is ongoing.
Rio Grande design work continues; renovation groundbreaking planned
Rio Grande Campus Building 1000 classrooms have closed, and faculty and staff are relocating to other campuses during the summer. The campus remains open to students, offering more than 100 classes in Building 3000. Design … Continue reading
Highland pre-construction work continues
Teams have completed design development. Abatement is complete and interior demolition is nearing completion. Crews have begun installing a separation wall to seal off the construction area. Construction is ongoing for temporary space in Building … Continue reading