January 2012: Elgin Campus Update

Elgin Campus December 2011

Dec. 6, 2011, aerial view. Photo courtesy of Aero Photo.

Elgin Campus January 2012

Jan. 10, 2012, aerial view. Photo courtesy of Aero Photo

Erosion controls are installed as well as the construction entrance and job trailer. Many truckloads of dirt have made their way to the site, and now Skanska is grading the site (including the building pad) and working on underground utilities. They expect to start drilling piers later this month. Recent rain has left the site too wet to work for a few days, but we remain on schedule as rain days were built into the construction schedule.

January 10, 2012, aerial view of campus site. Photo courtesy of Aero Photo

Back to Top