February 2012 – Elgin Campus Update

Installation of underground site utilities is well under way. All piers have been drilled and poured. The structural concrete has been poured for the area ways and elevator pit. The crawlspace mud slab will be poured the first week of March. Meanwhile, the submittal review process is ongoing.

Back to Top

4 Responses to "February 2012 – Elgin Campus Update"