We have started to go vertical! Steel erection began April 19. The building will be erected in three sections from floor to roof. It is expected to be complete by early June.
One of the driveways and the south parking lot will be poured by the end of April. The north parking lot and two other driveways will follow.
Skanska is constructing a mock wall to demonstrate all components of the walls, windows, roof, etc. for critique and approval by the architect and design team before actual wall construction.
We are starting to focus on furniture, fixtures, and equipment (FF&E) for the campus. We are meeting with all of the user groups to compose a list of FF&E items.
Back to Top
By Rebekah May 3, 2012 - 4:39 pm
Will mcdade and Paige residents be considered in district once the Elgin campus is built??
By ACC Staff May 3, 2012 - 5:27 pm
Hi Rebekah, the Elgin annexation was conducted by school district, so in order to be considered in-district in this case, you would need to reside in Elgin ISD. In-district communities are Austin ISD, Leander ISD, Manor ISD, Del Valle ISD, Round Rock ISD, Elgin ISD, Hays CISD, and the city of Austin.