Construction updates at Highland and Rio Grande: October 2019

Rio Grande Campus Renovations By: Paul Mason, Rio Grande Renovation Project Manager Work on Rio Grande Campus Building 1000 is proceeding along smoothly this month. ELECTRICALElectrical panel rough-in at the main electrical room is complete. … Continue reading

September Bond Projects Update

Construction crews at Highland Phase 2 and Rio Grande campuses have been hard at work this summer to make progress on the sites. Highland Campus Phase 2 constructionBy: Pamela Collier, ACC Highland Phase 2 Project … Continue reading

Construction begins at ACC Highland, Building 3000

Construction is underway at ACC Highland, Building 3000 (HLC 3000), the former women’s Dillard’s. The 185,000-square-foot building will be developed in phases. The first phase will serve as home to the new ACCTV studios and … Continue reading

Construction updates at Highland and Rio Grande: August 2019

What’s new at Highland Phase 2?By: Pamela Collier, ACC Highland Phase 2 Project Manager All aspects of construction have progressed as the building is large and in various stages of construction from one end to … Continue reading

Crews continue renovation work at ACC Highland Phase 2 and Rio Grande Campus

ACC Highland Phase 2 Construction crews continue to work over the summer on the Highland Campus Phase 2 renovation project, including waterproofing exterior openings, pouring sound slabs and ramps, open stair steel installation, and reinstalling … Continue reading

Rio Grande renovations continue at steady pace

Construction crews continue to make progress on the Rio Grande Campus renovations. In May, shoring — the process of temporarily supporting a building with props during alterations — was completed at the south mechanical room … Continue reading

May 2019 Bond Projects Update

Highland Campus Phase 2 ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior … Continue reading

Bond project construction updates: Highland and Rio Grande

ACC continues to make progress on $386 million in capital improvement projects approved by ACC District voters in the November 2014 bond election. In 2018, the college celebrated expanding to Leander with the opening of … Continue reading

Highland road closures begin March 12

ACC Highland will experience campus road closures beginning Monday, March 12, due to ongoing construction. Closures are: Denson Drive between Airport Boulevard and Highland Campus Drive. Portions of Highland Campus Drive between Denson and Clayton drives. … Continue reading

Celebrating progress: RRC topping out celebration marks construction milestone

ACC and its construction partners celebrated progress at Round Rock Campus Phase 2 with a topping out celebration Friday, September 15, 2017.   Construction crews, crafts workers, architects, engineers, and others on the project team … Continue reading