Construction crews continue work on Highland Campus Phase 2. Structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo canopy … Continue reading
March Progress Report: Framing and MEP continues at ACC Highland and Rio Grande campuses
Highland Phase 2 At ACC Highland Phase 2, construction teams continue work on framing, steel erection, and the exterior shell. Exterior window installation also continues, along with mechanical, electrical, and plumbing work. Rio Grande Campus … Continue reading
Highland and Rio Grande bond project updates: February 2019
Austin Community College (ACC) continues to move forward on phase 2 of the Highland Mall redevelopment and the renovation of Rio Grande Campus. Both projects are part of the capital improvement projects approved by district … Continue reading
ACC Highland redevelopment update
Renovation work continues on ACC Highland Phase 2. Demolition of the southeast portion of the building is complete, and construction on the college’s drama and dance departments and assembly areas for occupancy load, vibration, and … Continue reading
Bond project construction updates: Highland and Rio Grande
ACC continues to make progress on $386 million in capital improvement projects approved by ACC District voters in the November 2014 bond election. In 2018, the college celebrated expanding to Leander with the opening of … Continue reading
2018 Year In Review
2018 has been an eventful year for Austin Community College. The college opened one new campus and three new buildings, launched its first bachelor degree program, established exciting new partnerships, completed its website redesign, and … Continue reading
Lumina Focus: College Reshapes Shopping Mall and Students are Buying
Lumina Focus: College Reshapes Shopping Mall and Students are Buying COLLEGE RESHAPES SHOPPING MALL – AND STUDENTS ARE BUYING AUSTIN, Texas — Where shoppers once roamed the aisles of a JCPenney, students at Austin Community … Continue reading
Bond projects update: Construction begins at Highland; San Gabriel crews begin installing drywall; Round Rock tops out
Work is progressing on voter-approved bond projects districtwide. Read summaries below and stay-up-to-date on each project through the ACC Bond Construction Projects website. Highland Phase 2: Construction begins Construction is set to begin on ACC … Continue reading
Groundbreaking marks beginning of Highland Phase 2
Construction is set to begin on Austin Community College (ACC) Highland phase 2 that will add advanced facilities to prepare students for high-demand careers and nurture local business growth. Community leaders and friends joined ACC … Continue reading
ACC Highland campus enters phase two
KXAN: ACC Highland campus enters phase two ACC Highland campus enters phase two AUSTIN (KXAN) — Austin’s old Highland Mall is going from shopping center to learning center, with the second phase of Austin Community … Continue reading