Rio Grande Campus renovation - ACC Newsroom

Crews continue renovation work at ACC Highland Phase 2 and Rio Grande Campus

ACC Highland Phase 2 Construction crews continue to work over the summer on the Highland Campus Phase 2 renovation project, including waterproofing exterior openings, pouring sound slabs and ramps, open stair steel installation, and reinstalling … Continue reading

Rio Grande renovations continue at steady pace

Construction crews continue to make progress on the Rio Grande Campus renovations. In May, shoring — the process of temporarily supporting a building with props during alterations — was completed at the south mechanical room … Continue reading

May 2019 Bond Projects Update

Highland Campus Phase 2 ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior … Continue reading

Highland and Rio Grande bond project updates: April 2019

Construction crews continue work on Highland Campus Phase 2. Structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo canopy … Continue reading

March Progress Report: Framing and MEP continues at ACC Highland and Rio Grande campuses

Highland Phase 2 At ACC Highland Phase 2, construction teams continue work on framing, steel erection, and the exterior shell. Exterior window installation also continues, along with mechanical, electrical, and plumbing work.  Rio Grande Campus … Continue reading

Highland and Rio Grande bond project updates: February 2019

Austin Community College (ACC) continues to move forward on phase 2 of the Highland Mall redevelopment and the renovation of Rio Grande Campus. Both projects are part of the capital improvement projects approved by district … Continue reading

Bond project construction updates: Highland and Rio Grande

ACC continues to make progress on $386 million in capital improvement projects approved by ACC District voters in the November 2014 bond election. In 2018, the college celebrated expanding to Leander with the opening of … Continue reading

2018 Year In Review

2018 has been an eventful year for Austin Community College. The college opened one new campus and three new buildings, launched its first bachelor degree program, established exciting new partnerships, completed its website redesign, and … Continue reading

Bond Update: New Campuses open for fall classes

ACC invites faculty and staff to the grand opening celebration of Round Rock Campus Phase 2. The event will be 10 – 11:30 a.m. on Wednesday, September 26. The Round Rock celebration follows three other … Continue reading

Bond Projects Update: Elgin, Hays, Round Rock, Rio Grande, and San Gabriel

Work is progressing on voter-approved bond projects districtwide. Read summaries below and stay-up-to-date on each project through the ACC Bond Construction Projects website. Round Rock Phase 2 The parking lot is complete and open to the … Continue reading