ACC Eastview Campus Dental Hygiene Expansion on Schedule to Open this Fall

Austin Community College District (ACC) is on track to welcome more Dental Hygiene students this fall at the Eastview Campus. Construction of Phase 1 is officially complete, marking a major milestone in the project. Furniture … Continue reading →

Construction Reaches New Milestone at ACC Round Rock Campus

Austin Community College District (ACC) reaches a major milestone in the expansion of its Round Rock Campus. Foundations are now complete for both new buildings — Buildings 4000 and 5500. Vertical construction is expected to … Continue reading →

Photo of progress being made on bond project at Round Rock Campus

Construction Moves Forward on ACC Round Rock Campus 

Construction continues to progress on Austin Community College District’s (ACC) Applied Technology Expansion at the Round Rock Campus. This expansion project is part of ACC’s 2022 General Obligation Bond program to create state-of-the-art training facilities … Continue reading →

ACC Eastview Campus Dental Hygiene Expansion Moves Forward On Schedule

Austin Community College District (ACC) continues progressing steadily on the Dental Hygiene expansion project at its Eastview Campus. Construction is currently on schedule and within budget, with Phase 1 approximately 70% complete. This project is … Continue reading →

Progress Underway at ACC Round Rock Campus Expansion

Construction on the Austin Community College District (ACC) Round Rock Campus expansion is moving forward. As of the end of March, the project is approximately 15% complete, with site development work well underway. Crews have … Continue reading →

Construction underway to expand Dental Hygiene Program at Eastview Campus

The first phase of the 2022 General Obligation Bond projects at the Austin Community College District (ACC) Eastview Campus is in the construction phase. This project includes a significant expansion of its Dental Hygiene Program … Continue reading →

A group of people at box for groundbreaking with equipment behind them.

ACC Breaks Ground on First 2022 Bond Project to Expand Skilled Trades Education at Round Rock Campus

Austin Community College District (ACC) celebrated a milestone with a groundbreaking ceremony at its Round Rock Campus on Friday, November 22. The skilled trades project is the first project funded by the 2022 General Obligation … Continue reading →

Work on 2022 G.O. Bond resumes at Hays Campus 

Following an intentional pause of all 2022 General Obligation Bond projects, work is once again moving forward. The ACC Board of Trustees heard an update from ACC Chancellor Dr. Russell Lowery-Hart about plans to restart … Continue reading →

Round Rock Campus expansion design complete

Work is moving forward on the Applied Technology expansion at Austin Community College District (ACC) Round Rock Campus, near Building 5000. The design process began in September 2023, and the design development was completed in … Continue reading →

ACC Selects Construction Manager at Risk for Eastview Campus 

The Austin Community College District (ACC) Board of Trustees unanimously approved Linbeck Group, LLC as the construction manager at risk (CMAR) for the dental hygiene program expansion at the ACC Eastview Campus, at the regular … Continue reading →