Austin Community College District (ACC) has reached a major milestone in the Hays Campus expansion, with the Hays 5000 Phase 3 project now officially halfway through the Design Development stage. The project includes Building 5000 … Continue reading
Construction Advances on Round Rock Campus Applied Technology Expansion
Austin Community College District (ACC) continues to make progress on the Applied Technology expansion at the Round Rock Campus, one of the projects funded through the College’s 2022 General Obligation Bond. Work is underway on … Continue reading
Hays Campus Expansion Moves Forward as Design Work Advances
Austin Community College District (ACC) approaches a major milestone in the Hays Campus expansion. The schematic design phase for the new academic building is scheduled for completion by early November, marking an important step forward … Continue reading
Construction Progresses on ACC Round Rock Campus Applied Technology Expansion
Austin Community College District (ACC) continues to make progress on the Round Rock Campus Applied Technology expansion. This is one of the projects funded through the College’s 2022 General Obligation Bond. As of early October, … Continue reading
ACC Eastview Campus Dental Hygiene Expansion on Schedule to Open this Fall
Austin Community College District (ACC) is on track to welcome more Dental Hygiene students this fall at the Eastview Campus. Construction of Phase 1 is officially complete, marking a major milestone in the project. Furniture … Continue reading
Construction Reaches New Milestone at ACC Round Rock Campus
Austin Community College District (ACC) reaches a major milestone in the expansion of its Round Rock Campus. Foundations are now complete for both new buildings — Buildings 4000 and 5500. Vertical construction is expected to … Continue reading
Construction Moves Forward on ACC Round Rock Campus
Construction continues to progress on Austin Community College District’s (ACC) Applied Technology Expansion at the Round Rock Campus. This expansion project is part of ACC’s 2022 General Obligation Bond program to create state-of-the-art training facilities … Continue reading
ACC Eastview Campus Dental Hygiene Expansion Moves Forward On Schedule
Austin Community College District (ACC) continues progressing steadily on the Dental Hygiene expansion project at its Eastview Campus. Construction is currently on schedule and within budget, with Phase 1 approximately 70% complete. This project is … Continue reading
Progress Underway at ACC Round Rock Campus Expansion
Construction on the Austin Community College District (ACC) Round Rock Campus expansion is moving forward. As of the end of March, the project is approximately 15% complete, with site development work well underway. Crews have … Continue reading
Construction underway to expand Dental Hygiene Program at Eastview Campus
The first phase of the 2022 General Obligation Bond projects at the Austin Community College District (ACC) Eastview Campus is in the construction phase. This project includes a significant expansion of its Dental Hygiene Program … Continue reading

