December 2019 | Rio Grande Campus Renovations

Two large cranes are on site erecting the last structural steel members to frame out the rooftop penthouse and place the curved tube steel framing for the new atrium roofs. Within the building, the structural window jamb repair work is now complete. Exterior windows have been placed on the west, north, and east façades. About 75 percent of all the windows have now been installed. In the north atrium, the last few steel windows are being abated and cleaned for new paint. Repointing and repair of the existing building facades also continues, and is nearing completion.