Installation of electrical fixtures commenced this month and permanent power to the building was established on November 21. Installation of drywall and insulation on all three levels continued. Waterproofing work continued this month and is near completion. The installation of the hydraulic elevator commenced. The concrete subcontractor continued to form and place curb and gutter, sidewalks, and concrete paving.