Round Rock foundation work, steel framing to begin

The crawlspace excavation for the new building is complete and piers have been drilled and poured. The elevator pit slab has been placed and pit wall construction is ongoing. Crews also have begun installing underground site utilities.

The concrete slab for the building’s first floor is scheduled to be complete by the end of June, to be followed by the second and third floor slabs. Structural steel installation is scheduled to be complete mid-August.

SpawGlass, the project’s construction manager at-risk, is tweeting updates about the project using the Twitter handle @ACC_RR_Phase 2.