February 2019 | Rio Grande Campus Renovations

Construction crews continue work on the lower level, including mechanical/electrical/plumbing overhead and chilled beam installation. The mechanical room slab in the north atrium and the underground electrical duct bank have been poured. Interior wall framing … Continue reading

December 2018 | Rio Grande Campus Renovations

Construction crews are finalizing demolition of interior sections, most recently working on structural floor demolition. In addition, crews are installing hydronic piping and a new roof at the chiller house. In January, crews will continue … Continue reading

Board selects construction manager

ACC’s Board of Trustees selected Bartlett-Cocke as the construction-manager-at-risk for Rio Grande Campus. The firm, one of three finalists considered out of the 11 submitted proposals, oversaw Building 3000 renovations at Rio Grande Campus.