April 2019 | ACC Highland Phase 2

Construction crews continue work on Highland Campus Phase 2. The structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo canopy steel has been erected, and the loading dock slab and sidewalks have been placed. One additional chiller and cooling tower have been installed to the existing chiller plant. Steel roof decking is complete and roofing work and wall framing are underway. Drywall installation has begun on the lower level.