» phase 2ACC 2014 Bond Projects

May/June 2020 | ACC Highland Phase 2

The exterior walkways, seating walls, and landscaping are complete on the west and are underway on the east side. The exterior building finishes are being completed and exterior furnishings are forthcoming. The majority of the … Continue reading

February 2020 | ACC Highland Phase 2

Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. … Continue reading

December 2019 | ACC Highland Phase 2

Drywall work is nearing completion and elevator installation is wrapping up soon. Railings at floor openings and stairs are well underway. Crews are now installing restroom fixtures and toilet partitions. Installation is complete for the … Continue reading

November 2019 | ACC Highland Phase 2

Overhead doors are being installed and the majority of the exterior curtain wall and stucco work are completed. Exterior grading and flatwork have begun. The exterior and interior stair railings are currently being installed. The … Continue reading

October 2019 | ACC Highland Phase 2

The interior wall framing is almost complete and sheetrock work is expected to wrap by mid-November. Many interior walls have been primed and painted. Interior and exterior doors are being hung. Ceiling grid installation is … Continue reading

September 2019 | ACC Highland Phase 2

The chilled water pipes have been flushed and a portion of the building now has conditioned air. Interior finishes are progressing. The ceiling grid and light fixtures are beginning to be installed. The glass handrails … Continue reading

August 2019 | ACC Highland Phase 2

All aspects of construction have progressed as the building is large and in various stages of construction from one end to the other. Exterior curtain wall, storefront windows, and doors are being installed, and the … Continue reading

July 2019 | ACC Highland Phase 2

Construction crews continue to work over the summer on the Highland Campus Phase 2 renovation project, including waterproofing exterior openings, pouring sound slabs and ramps, open stair steel installation, and reinstalling permanent fencing around the … Continue reading

May 2019 | ACC Highland Phase 2

ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent … Continue reading

April 2019 | ACC Highland Phase 2

Construction crews continue work on Highland Campus Phase 2. The structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo … Continue reading