Drywall work is nearing completion and elevator installation is wrapping up soon. Railings at floor openings and stairs are well underway. Crews are now installing restroom fixtures and toilet partitions. Installation is complete for the majority of interior door and window frames as well for as the walk-in coolers and freezers for the culinary kitchens. Many of the faculty office suites are receiving finishes such as paint, carpet, millwork, and ceiling grid. In the southern portion of the building, overhead utilities are underway. The building exterior metal wall panel has begun in the Paseo.