November 2020 | ACC Highland Phase 2

Construction is substantially complete while final testing and commissioning of all systems are still ongoing. Final corrections/touchups and final cleaning are occurring as well. Departmental moves have begun and faculty and staff are starting to set up their spaces prior to the start of the spring semester beginning in January 2021. The building remains closed to the general public as there is still a lot of activity inside getting things finished and set up.

October 2020 | ACC Highland Phase 2

Construction is nearly substantially complete. Final testing and commissioning of all systems are still ongoing. Final corrections/touchups and final cleaning are occurring as well. The telescopic seating for the Dance Studio will be installed soon. Equipment is still being installed throughout the building and furniture is being placed in its correct location throughout also. Computer installation will be forthcoming. Departmental moves will begin soon so that faculty and staff may set up their spaces prior to the start of the spring semester beginning in January 2021.

September 2020 | ACC Highland Phase 2

The Black Box Theatre wood floor is being installed. The wood stage flooring in the Music Performance Hall will be installed soon. The fixed seating in the performance spaces is being installed. Final touches and last-minute finishes are being completed. The mechanical and electrical systems have had a final inspection. The plumbing and fire alarm systems are being tested and will be inspected soon. The majority of the furniture has been installed and equipment installation is well underway. The exterior furniture has been installed as well.

July/August 2020 | ACC Highland Phase 2

Construction is nearing completion with a substantial completion milestone expected at the end of September. Final touches are being completed throughout the building with several large performance spaces still undergoing substantial construction activities. Curtain tracks are being hung. The wood sprung dance floor will be installed soon. Fixed seating is starting to be installed in some locations. The pipe grid is nearly complete in all areas.

The connections to adjacent buildings 1000 and 4000 have been completed. Landscaping and site paving is mostly complete. Exterior furniture has been installed. The majority of the furniture has been delivered and installed. Equipment installation has begun in some areas.

ACC Highland: First park opens Saturday, May 12

Highland Greenway Park

The first of three parks for Highland will open to the community Saturday, May 12. A kick-off celebration is scheduled for 1 to 3 p.m. at the Highland Greenway Park, located off Clayton Lane next to the Elan Parkside apartment complex. Families, students, and faculty and staff are invited to explore the two-acre park. The event includes food and beverages from Easy Tiger and Kick Butt Coffee. Families are invited to participate in lawn games and enjoy the lush green landscape. For more information, visit the Highland Redevelopment Project website.