» Phase IIACC 2014 Bond Projects

May/June 2020 | ACC Highland Phase 2

The exterior walkways, seating walls, and landscaping are complete on the west and are underway on the east side. The exterior building finishes are being completed and exterior furnishings are forthcoming. The majority of the … Continue reading

Crews begin construction

Construction crews have started the next phase of development at Elgin Campus. Site work for the project currently includes moving dirt, trenching, leveling off land, etc. Phase 2 is scheduled to be completed for classes … Continue reading

Board selects construction manager for Phase 2

ACC’s Board of Trustees selected JT Vaughn Construction as the construction manager for Hays Campus Phase 2. The firm, one of three finalists considered out of the 10 submitted proposals, have completed more than 600 … Continue reading

Board selects Elgin Campus Phase 2 Construction-Manager-At-Risk

ACC’s Board of Trustees selected DPR Construction as the construction-manager-at-risk for Elgin Campus Phase 2. The firm, one of three finalists considered out of the four submitted proposals, recently completed the UT Animal Resources Center and the UT … Continue reading

End-of-year update on Elgin Campus

The Elgin Campus architectural design firm met with the campus’ steering committee on Friday, December 4, to begin planning for the $8.9 million expansion project. Discussions focused on unique needs of the college’s Veterinary Technology … Continue reading

Board selects SpawGlass for Phase 2

ACC’s Board of Trustees selected SpawGlass as the construction manager at-risk for Round Rock Campus Phase 2. The firm, one of four finalists considered out of the eight submitted proposals, oversaw Round Rock Campus Phase 1 … Continue reading

Board selects Brinkley Sargent Wiginton for Phase 2

ACC’s Board of Trustees selected Brinkley Sargent Wiginton as the architect/engineering firm for Hays Campus Phase 2. The firm, one of three finalists considered out of the seven submitted proposals, will oversee construction of the … Continue reading

Elgin Campus

Board selects O’Connell Robertson for Phase 2

ACC’s Board of Trustees selected O’Connell Robertson as the architect/engineering team for Elgin Campus Phase 2. The firm, one of three finalists considered out of the four submitted proposals, oversaw Phase 1 at Elgin Campus … Continue reading

Board selects architect/engineering team

ACC’s Board of Trustees selected Studio 8 Architects (HUB) as the lead architect/engineering team for Rio Grande Campus. The firm is one of three finalists considered out of the 12 submitted proposals. Studio 8 Architects … Continue reading

Back to Top