Overhead doors are being installed and the majority of the exterior curtain wall and stucco work are completed. Exterior grading and flatwork have begun. The exterior and interior stair railings are currently being installed. The … Continue reading
October 2019 | ACC Highland Phase 2
The interior wall framing is almost complete and sheetrock work is expected to wrap by mid-November. Many interior walls have been primed and painted. Interior and exterior doors are being hung. Ceiling grid installation is … Continue reading
September 2019 | ACC Highland Phase 2
The chilled water pipes have been flushed and a portion of the building now has conditioned air. Interior finishes are progressing. The ceiling grid and light fixtures are beginning to be installed. The glass handrails … Continue reading
August 2019 | ACC Highland Phase 2
All aspects of construction have progressed as the building is large and in various stages of construction from one end to the other. Exterior curtain wall, storefront windows, and doors are being installed, and the … Continue reading
July 2019 | ACC Highland Phase 2
Construction crews continue to work over the summer on the Highland Campus Phase 2 renovation project, including waterproofing exterior openings, pouring sound slabs and ramps, open stair steel installation, and reinstalling permanent fencing around the … Continue reading
May 2019 | ACC Highland Phase 2
ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent … Continue reading
April 2019 | ACC Highland Phase 2
Construction crews continue work on Highland Campus Phase 2. The structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo … Continue reading
March 2019 | ACC Highland Phase 2
At ACC Highland Phase 2, construction teams continue work on framing, steel erection, and the exterior shell. Exterior window installation also continues, along with mechanical, electrical, and plumbing work.
February 2019 | ACC Highland Phase 2
Construction continues on phase 2 at ACC Highland. Crews completed the removal of floor finishes in January and are now re-pouring concrete that was in disrepair. Work also continues on the new television studio and … Continue reading
January 2019 | ACC Highland Phase 2
Demolition of the southeast portion of the building is complete, and construction on the college’s drama and dance departments and assembly areas for occupancy load, vibration, and clear-span of columns/beams is underway. Steel erection, roofing, … Continue reading