HLC2 is complete, except for minor touch-ups and testing/commissioning, and open for the spring semester.
November 2020 | ACC Highland Phase 2
Construction is substantially complete while final testing and commissioning of all systems are still ongoing. Final corrections/touchups and final cleaning are occurring as well. Departmental moves have begun and faculty and staff are starting to … Continue reading
October 2020 | ACC Highland Phase 2
Construction is nearly substantially complete. Final testing and commissioning of all systems are still ongoing. Final corrections/touchups and final cleaning are occurring as well. The telescopic seating for the Dance Studio will be installed soon. … Continue reading
September 2020 | ACC Highland Phase 2
The Black Box Theatre wood floor is being installed. The wood stage flooring in the Music Performance Hall will be installed soon. The fixed seating in the performance spaces is being installed. Final touches and … Continue reading
July/August 2020 | ACC Highland Phase 2
Construction is nearing completion with a substantial completion milestone expected at the end of September. Final touches are being completed throughout the building with several large performance spaces still undergoing substantial construction activities. Curtain tracks … Continue reading
May/June 2020 | ACC Highland Phase 2
The exterior walkways, seating walls, and landscaping are complete on the west and are underway on the east side. The exterior building finishes are being completed and exterior furnishings are forthcoming. The majority of the … Continue reading
March/April 2020 | ACC Highland Phase 2
The Riverbat has been installed on the Paseo canopy. It casts a shadow below that moves across the Paseo throughout the day. Concrete placement on the west side is finishing up. Grading and concrete work … Continue reading
February 2020 | ACC Highland Phase 2
Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. … Continue reading
January 2020 | ACC Highland Phase 2
Interior Gas service is now on in the building and plumbing fixtures are being installed. Overhead utilities are still underway in the southern portion of the building. Restroom tilework is making progress, as well as … Continue reading
Highland pre-construction work continues
Teams have completed design development. Abatement is complete and interior demolition is nearing completion. Crews have begun installing a separation wall to seal off the construction area. Construction is ongoing for temporary space in Building … Continue reading