February 2020 | ACC Highland Phase 2

Interior finishes and specialties are being installed and drywall finishing is ongoing. Overhead acoustical panel installation is ongoing. Cabinetry and built-in desks continue to be installed. Culinary equipment is being installed. Signage installation has begun. Restroom accessory installation is about to begin. Tile work, carpet, and other flooring activities are ongoing. Decorative metal railing posts have been installed at the open stairs and perforated panels will be installed in March. Glass railing at floor openings is complete. Three of the five elevators are complete. Cable tray installation, wire pulling, and pipe insulation are nearly complete.

Exterior metal panel activities are ongoing on the upper paseo. Paseo waterproofing is nearly complete and elevated concrete topping slab will be poured soon afterward. Sitework is currently ongoing in the paseo and on the west side. Sidewalks are being installed. Landscaping and finishes to begin shortly.